October 2023 is the contractor’s required substantial completion of construction activities in all phases of the Project. The contractor is required to open the trail for public use by October 2023, with minor correctional items of work to be completed within the phases. January 2024 is the final Project completion date and all activities will be completed by then. 

However, the contractor is currently trying to complete items in Phase 1 in order to have the Phase 1 of the trail available for public use by April 2023. 

As the project continues to move closer to completion, the anticipated project construction schedule will be updated more frequently to reflect a more accurate estimated timeline for the levee trail reopening. The project team anticipated shifts to the construction schedule depending on various factors such as weather or other unforeseen circumstances.